4) The managerial accountant at Sailboat World compiles a monthly overhead variance 4) report. The company produced 30,584 sailboats in the past month at 0.28
4) The managerial accountant at Sailboat World compiles a monthly overhead variance 4) report. The company produced 30,584 sailboats in the past month at 0.28 machine hours per unit. The budgeted fixed overhead cost was $95,000 whereas actual fixed overhead cost was $96,400. Calculate the standard fixed overhead cost allocated to production at $11 per machine-hour. Compute the fixed overhead volume variance and the fixed overhead budget variance