Question

1 Approved Answer

4.1. The following table represents data of a project you are working on: Activity Predecessor Most optimistic Most likely Most pessimistic Time in days A

4.1.The following table represents data of a project you are working on:

Activity Predecessor Most optimistic Most likely Most pessimistic


Time in days
A _ 4 8 24
B _ 3 10 11
C _ 6 12 24
D A;B 9 14 25
AND B;C 11 16 27
F D. E 13 15 35
G F 5 9 19
H G 7 15 23


Required:

4.1 Using the PERT formula, calculate the time (t) for each activity. (5)

4.2 Construct the network using the AON methodology. (10)

4.3 Identify the parts and indicate the critical path. (5)

4.4 Explain the advantages of using network diagrams rather than Gantt Charts. (5)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

1 Using the PERT formula the t time for each activity is given in below table 42 The Network diagram using AON Activity on Node format is given below ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Income Tax Fundamentals 2013

Authors: Gerald E. Whittenburg, Martha Altus Buller, Steven L Gill

31st Edition

1111972516, 978-1285586618, 1285586611, 978-1285613109, 978-1111972516

More Books

Students also viewed these General Management questions

Question

Can public works increase equilibrium wages?

Answered: 1 week ago

Question

What other bills do I have to pay?

Answered: 1 week ago

Question

Find the inverse, if it exists, for the matrix. -1

Answered: 1 week ago