42.You can quickly view any individual task bar by selecting the task on the left of the Gantt Chart view and then: A.clicking Add to

42.You can quickly view any individual task bar by selecting the task on the left of the Gantt Chart view and then:

A.clicking Add to Timeline on the View tab in MS Project

B.clicking Scroll to Task on the View tab in MS Project

C.clicking Gantt Chart view on the Task or View tabs in MS Project

D.clicking Scroll to Task on the Task tab in MS Project

43.The Timeline View is one way to convey a quick summary of the project plan.

TRUE

FALSE

44. The bar chart of the Gantt Chart view defaultly consists of all of the following EXCEPT:

A.units of time

B.link lines

C.timescale band

D.graphical bars

E.symbols

F.task names

45.Using the Drawing tool for the chart portion of a Gantt Chart, you can draw all of the following shapes EXCEPT:

A.Oval.

B.Lin

C.Arrow

D.Gantt bar

E.Arc

F.Rectangle

G.Textbox

H.Polygon

46.When tracking by recording a task's actual duration, all of the following are true EXCEPT:

A.All of the other answers are true

B.If the actual duration is less than the scheduled duration, the new scheduled duration is the amount that remains

C.If the actual duration is longer than the scheduled duration, the task is set to fully completed

D.If the actual duration is the same as the scheduled duration, the task is set to fully completed

47.WHICH of the following tables displays a comparison of the scheduled and baseline details (start and finish only) side by side?

A.Variance

B.Baseline

C.Entry

D.Schedule

E.Gantt Chart view

F.Tracking

48.A project cannot be properly managed without both effective planning and then tracking actual performance.

TRUE

FALSE

49. It is normal and acceptable for project team members to each have a different idea of what constitutes the completion of a task.

TRUE

FALSE

50. When you update the project plan with actual values, the schedule changes due to differences. The baseline representing the original plan also changes to reflect what actually occurred.

TRUE

FALSE

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cases In Human Resource Management In Hospitality

Authors: Shirley Gilmore

1st Edition

0131119834, 9780131119833

More Books

Students also viewed these General Management questions

Question

Distinguish between the roles of the FRC and the AASB.

Answered: 1 week ago

Question

5. How can I help others in the network achieve their goals?

Answered: 1 week ago