. ( 5 0 ) A contractor has 3 0 workers on the construction site for a specific task, which is behind schedule ( 2

.(50) A contractor has 30 workers on the construction site for a specific task, which is
behind schedule (2 weeks delay). They work 8 hours work and 5 days per week based on
$15 hourly salary. The liquidate damage is $2,000 per day. You should show the
calculation process to get full credits (10 points)
A contractor needs to make a decision whether the schedule should be accelerated based
on the overtime work (12 hours per day and 5 days per week) or just leave the schedule.
Overtime payment is 2 times of the base hourly salary. What is your choice based on the
expected value?
(Hint: You need to consider the overtime payment as well as the lost value on your
productivity. Then you can compare total expected lost value and total liquidate damage
for delay)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these General Management questions