Question
1 Approved Answer
5 . 1 7 . A steady - state Rankine cycle currently in service operates as follows: Steam leaves the boiler at P = 8
A steadystate Rankine cycle currently in service operates as follows:
Steam leaves the boiler at bar and
Steam leaves the turbine as saturated vapor at bar.
Water leaves the condenser as saturated liquid at bar.
Water leaving the condenser is pumped up to bar and returned to the boiler.
The power output FROM THE TURBINE is MW
Your company has the opportunity to upgrade the turbine to one that is efficient, at a cost of $ million. This includes all costs associated with the replacementthe new equipment, installation, instrumentation, etc. If the upgrade is done it will work this way:
The flow rate, temperature, and pressure of the steam entering the turbine will all be unchanged, but the turbine is expected to produce more work.
The pressure leaving the turbine will still be bar, but won't necessarily be saturated vapor, since the turbine is now removing more energy as work.
The in the condenser will be adjusted such that the water leaving the turbine is saturated liquid, allowing the pump and boiler to operate EXACTLY the same in the upgraded cycle as they do in the current cycle.
The current turbine produces of power, hours a day, for days per year. The company values any "extra" work produced beyond this at $GJ
A Determine the flow rate at which watersteam circulates through the process.
B Determine the efficiency of the turbine in the CURRENT cycle.
C Determine the overall efficiency of the CURRENT cycle.
D Determine the power produced by the turbine in the UPGRADED cycle.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started