5. [30 points] Consider a project with following precedence relationships and activity times. Activity Immediate Predecessor...
Fantastic news! We've Found the answer you've been seeking!
Question:
![image text in transcribed](https://s3.amazonaws.com/si.experts.images/answers/2024/05/66479d842f86f_41166479d83edf73.jpg)
Transcribed Image Text:
5. [30 points] Consider a project with following precedence relationships and activity times. Activity Immediate Predecessor Optimistic Time Most Likely Pessimistic Time Time A 2 2.5 6 B 10 11 12 A 5 6.5 11 D B, C 11 13 15 E B 8 9.5 14 F D 4.5 5.5 9.5 G E 3.5 5 6.5 H F, G 6.5 7.5 11.5 a. Calculate the expected activity duration (t), variance for each activity, ES, EF, LS, and LF times and the slack for each activity. Show the values in a table (activity schedule). What is the critical path for the project? Show all work to earn credit. b. What is the probability of completing the project in 35 weeks? Show all work to earn credit. c. If the activity B can be finished in 10 weeks, D in 11 weeks, and E in 8 weeks, recalculate the expected project completion time. Show all work. d. Using MS Project (or any other software), create a Gantt chart for the project based on ES and EF times. If you worked in a paper, you must scan the work and insert it into the .docx or .pdf file with your answers. Separate images of documents are not accepted. 5. [30 points] Consider a project with following precedence relationships and activity times. Activity Immediate Predecessor Optimistic Time Most Likely Pessimistic Time Time A 2 2.5 6 B 10 11 12 A 5 6.5 11 D B, C 11 13 15 E B 8 9.5 14 F D 4.5 5.5 9.5 G E 3.5 5 6.5 H F, G 6.5 7.5 11.5 a. Calculate the expected activity duration (t), variance for each activity, ES, EF, LS, and LF times and the slack for each activity. Show the values in a table (activity schedule). What is the critical path for the project? Show all work to earn credit. b. What is the probability of completing the project in 35 weeks? Show all work to earn credit. c. If the activity B can be finished in 10 weeks, D in 11 weeks, and E in 8 weeks, recalculate the expected project completion time. Show all work. d. Using MS Project (or any other software), create a Gantt chart for the project based on ES and EF times. If you worked in a paper, you must scan the work and insert it into the .docx or .pdf file with your answers. Separate images of documents are not accepted.
Expert Answer:
Posted Date:
Students also viewed these general management questions
-
En cunto tiempo se acumularn $200000 mediante depsitos bimestrales vencidos de $5000 si se invierten a una tasa de 7% anual convertible bimestralmente?
-
By using MS Project answer the following Q with Screen shot for each Q Information for Network Construction INFORMATION FOR PROJECT DELTA Activity Description Predecessors Estimated Duration A...
-
The accounting break-even point is that level of sales where (2 Points) Total revenues equal total costs. EBIT equals depreciation expense, and cash flow equals zero. Sales revenue equals variable...
-
All administrative laws are criminal laws and enforceable as such even though they are not part of the Criminal Code. True False
-
Susans Bake Shop bought a new air-conditioning system when the old one stopped working. The invoice price of the system was $45,000. Susans also had the following expenses associated with the...
-
Three events pertaining to Lean Machine Co. are described below. a. Issued common stock for cash. b. The market value of the corporations stock increased. c. Declared and paid a cash dividend to...
-
How do joint costs differ from other common costs? LO1
-
Flanagan Company reports the following for the month of June. Instructions(a) Calculate the cost of the ending inventory and the cost of goods sold for each cost flow assumption, using a perpetual...
-
Q2 Approximately one year ago, a married couple went to an attorney, Blithe Freedman, Esq., and stated that they wished to obtain a divorce. The parties told Attorney Freedman that they had agreement...
-
A person moves from the origin along the positive y-axis pulling a weight at the end of a 12-meter rope (see figure). Initially, the weight is located at the point (12, 0). (a) Show that the slope of...
-
Sunshine Stadium Revenue 4.5 4.8 6 4.4 4.2 4.7 $100,000's 1.8 1.3 1.4 1.5 1.1 0.8 0.6 0.6 0.7 0.5 0 2014 2015 2016 2017 2018 (Predicted) Merchandise Food Drinks Year Annual Attendance (100,000's)...
-
Water at \(10^{\circ} \mathrm{C}\) flows in a \(1.2-\mathrm{cm}\)-diameter pipe at a rate of \(1.33 \mathrm{~L} / \mathrm{min}\). The hydrodynamic entry length is (a) \(0.60 \mathrm{~m}\) (b) \(0.94...
-
Air at \(1 \mathrm{~atm}\) and \(20^{\circ} \mathrm{C}\) flows in a 3-cm-diameter tube. The maximum velocity of air to keep the flow laminar is (a) \(0.87 \mathrm{~m} / \mathrm{s}\) (b) \(0.95...
-
Hot combustion gases approximated as air at \(1 \mathrm{~atm}\) and \(350^{\circ} \mathrm{C}\) flow in a \(16-\mathrm{cm}\)-diameter steel pipe at a velocity of \(3.5 \mathrm{~m} / \mathrm{s}\). The...
-
In the midst of closing procedures, Park Corporation's accountant became ill and was hospitalized. You have volunteered to complete the closing of the books, and you find that all revenue and expense...
-
Closing Entries Use the information provided in E3-11A to prepare journal entries to close the accounts using the Income Summary account. After these entries are posted, what is the balance in the...
-
A test of emotional intelligence was given to 241 women and 89 men. The results were as follows: For women, M= 96.62, SD = 10.34; for men, M= 89.33, SD= 11.61. Was this difference statistically...
-
Consider the following cash flows in Table P5.5. (a) Calculate the payback period for each project. (b) Determine whether it is meaningful to calculate a payback period for project D. (c) Assuming...
-
When do ABC and traditional methods yield similar results? Refer to Exercise 30. In general, under what circumstances would the two allocation methods in parts a. and b. result in similar profit...
-
ABC versus traditional costing. Vicki Greenshade. CPA. provides consulting and tax preparation services to her clients. She charges a fee of $100 per hour for each service. Her revenues and expenses...
-
Resources used versus resources supplied. Information about two activities for the Condor Corporation follows: Compute unused capacity for energy and marketing. Resources Used Energy. Marketing...
![Mobile App Logo](https://dsd5zvtm8ll6.cloudfront.net/includes/images/mobile/finalLogo.png)
Study smarter with the SolutionInn App