5) A highway contractor needs to locate a single supply point to provide road building materials to three projects. The volume and the map
5) A highway contractor needs to locate a single supply point to provide road building materials to three projects. The volume and the map coordinates for the three projects are shown below. Find the ideal location (coordinates) of the supply point using Center of Gravity Method. Collection point Load (X,Y) Coordinates A 8,000 (3,8) B 5,000 (7,4) C 12,000 (6,1)
Step by Step Solution
There are 3 Steps involved in it
Step: 1