5 A project manager wraps up the execution phase of a project and needs to schedule a meeting to reflect on what went well and
5 A project manager wraps up the execution phase of a project and needs to schedule a meeting to reflect on what went well and potential improvements for the future. What type of meeting can they schedule? 1 point Project kickoff Project status updates Retrospective Stakeholder review