Question
5. Draw the project network for the following activities in a project. [15 M] a. Determine the expected project completion time and the critical
5. Draw the project network for the following activities in a project. [15 M] a. Determine the expected project completion time and the critical path of the project. b. Determine the variance of the expected project completion time. c. What is the probability that the project will be completed on or before 104 weeks? A B C (From Standard normal distribution table, P (0.41) = 0.34090; P (0.42) = 0.33724; P (0.17)=0.33360) Activity D E F G H I J Predecessor A A B B,C B D,E F,G B,C I.H Optimistic time (weeks) Most likely time (weeks) 4 10 7 13 19 4 13 13 16 19 16 13 19 22 19 25 35 7 13 Pessimistic time (weeks) 28 25 37 37 33 33 19 49 37 19
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Introduction to Operations Research
Authors: Frederick S. Hillier, Gerald J. Lieberman
10th edition
978-0072535105, 72535105, 978-1259162985
Students also viewed these General Management questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App