5). If you miscalculated the Slack Time (L-E start and L-E finish) and 2 critical activities are missing on your critical path, which of the
5). If you miscalculated the Slack Time (L-E start and L-E finish) and 2 critical activities are missing on your critical path, which of the followins will happen? | |||||||
A). A 50% chance that the project's completion dates will be shorter than correct ones; | |||||||
B). A 99% chance of on-time completion date will be longer than the correct one; | |||||||
C). The project's standard deviation will become larger; thus, the number of standard deviations (Z score) the target date lies from the mean will become smaller; | |||||||
D). On the project completion times' normal probability distribution curve, the time between your 99% chance vs. 50% chance completion date will be shorter; t | |||||||
E). The project will have more non-critical ativities than expected. |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started