5. In a CPM network, the critical path has five activities. Their durations are tabulated next. Compute the following: a. The probability that the project
5. In a CPM network, the critical path has five activities. Their durations are tabulated next.
Compute the following:
a. The probability that the project will finish by the end of day 32.
b. The probability that the project will finish by the end of day 34.
c. The probability that the project will finish before day 30.
d. The probability that the project will finish on day 32.
e. The probability that the project will finish no later than day35.
f. The probability that the project will finish at least 2 days early.
g. The probability that the project will finish at least 2 days late.
h. The probability that the project will finish on day 32 1 day.
i. The completion date with at least a 90% confidence level.
\begin{tabular}{lccc} \hline & \multicolumn{3}{c}{ Duration (Days) } \\ \cline { 2 - 4 } Activity & Optimistic (To) & Most Likely (Tm) & Pessimistic (Tp) \\ \hline A & 2 & 5 & 9 \\ B & 3 & 4 & 8 \\ C & 4 & 6 & 9 \\ D & 5 & 10 & 20 \\ E & 3 & 5 & 9 \\ \hline \end{tabular}Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started