Question

1 Approved Answer

5 skilled workers can build a wall in 20 days; 8 semi-skilled worker can build a wall in 25 days; 10 unskilled workers can

image

5 skilled workers can build a wall in 20 days; 8 semi-skilled worker can build a wall in 25 days; 10 unskilled workers can build a wall in 30 days. If a team has 2 skilled, 6 semi-skilled and 5 unskilled workers, how long will it take to build the wall? (A) 20 days (C) 16 days (B) 18 days (D) 15 days

Step by Step Solution

3.34 Rating (148 Votes )

There are 3 Steps involved in it

Step: 1

Answer The correct option is D 15 days Per day wor... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Microeconomics Theory and Applications with Calculus

Authors: Jeffrey M. Perloff

3rd edition

133019934, 978-0133019933

More Books

Students also viewed these Chemical Engineering questions

Question

What activities do you enjoy when you are not working?

Answered: 1 week ago

Question

What are the functions of top management?

Answered: 1 week ago

Question

Bring out the limitations of planning.

Answered: 1 week ago

Question

Why should a business be socially responsible?

Answered: 1 week ago

Question

Discuss the general principles of management given by Henri Fayol

Answered: 1 week ago