Question
5 skilled workers can build a wall in 20 days; 8 semi-skilled worker can build a wall in 25 days; 10 unskilled workers can
5 skilled workers can build a wall in 20 days; 8 semi-skilled worker can build a wall in 25 days; 10 unskilled workers can build a wall in 30 days. If a team has 2 skilled, 6 semi-skilled and 5 unskilled workers, how long will it take to build the wall? (A) 20 days (C) 16 days (B) 18 days (D) 15 days
Step by Step Solution
3.34 Rating (148 Votes )
There are 3 Steps involved in it
Step: 1
Answer The correct option is D 15 days Per day wor...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Microeconomics Theory and Applications with Calculus
Authors: Jeffrey M. Perloff
3rd edition
133019934, 978-0133019933
Students also viewed these Chemical Engineering questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App