Question

1 Approved Answer

5. Tombro Industries is in the process of automating one of its plants and developing a flexible manufacturing system. The company is finding it necessary

5.

Tombro Industries is in the process of automating one of its plants and developing a flexible manufacturing system. The company is finding it necessary to make many changes in operating procedures. Progress has been slow, particularly in trying to develop new performance measures for the factory.

In an effort to evaluate performance and determine where improvements can be made, management has gathered the following data relating to activities over the last four months:

Month

1 2 3 4
Quality control measures:
Number of defects 190 150 110 100
Number of warranty claims 58 40 25 14
Number of customer complaints 110 110 120 110
Material control measures:
Purchase order lead time 12 days 7 days 5 days 4 days
Scrap as a percent of total cost 3.4 % 2.9 % 3.2 % 2.7 %
Machine performance measures:
Machine downtime as a percentage of availability 81 % 80 % 80 % 79 %
Use as a percentage of availability 75 % 73 % 69 % 70 %
Setup time (hours) 2.3 2.3 2.3 2.3
Delivery performance measures:
Throughput time ? ? ? ?
Manufacturing cycle efficiency (MCE) ? ? ? ?
Delivery cycle time ? ? ? ?
Percentage of on-time deliveries 85 % 88 % 91 % 96 %

The president has read in industry journals that throughput time, MCE, and delivery cycle time are important measures of performance, but no one is sure how they are computed. You have been asked to assist the company, and you have gathered the following data relating to these measures:

Average per Month (in days)

1 2 3 4
Wait time per order before start of production 15.6 15.0 12.1 9.0
Inspection time per unit 0.2 0.5 0.5 0.6
Process time per unit 0.5 0.5 0.5 0.5
Queue time per unit 5.5 5.6 5.5 5.6
Move time per unit 1.5 1.4 1.4 1.5

Required:
1-a. Compute the throughput time for each month. (Round your answers to 1 decimal place.)

1-b.

Compute the manufacturing cycle efficiency (MCE) for each month. (Round your answers to 1 decimal place (i.e., 0.123 should be entered as 12.3).)

1-c.

Compute the delivery cycle time for each month. (Round your answers to 1 decimal place.)

3-a.

Refer to the inspection time, process time, and so forth, given for month 4. Assume that in month 5 the inspection time, process time, and so forth, are the same as for month 4, except that the company is able to completely eliminate the queue time during production using Lean Production. Compute the new throughput time and MCE. (Round your Throughput Time to 1 decimal place. Round your MCE percentage answer to 1 decimal place (i.e., 0.123 should be entered as 12.3).)

3-b.

Refer to the move time, process time, and so forth, given for month 4. Assume that in month 6 the inspection time, process time, and so forth, are the same as in month 4, except that the company is able to eliminate both the queue time during production and the inspection time using Lean Production. Compute the new throughput time and MCE. (Round your Throughput Time to 1 decimal place. Round your MCE percentage answer to 1 decimal place (i.e., 0.123 should be entered as 12.3).)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamental Accounting Principles Volume 2

Authors: Kermit Larson, Heidi Dieckmann

15th Canadian Edition

1259087360, 9781259087363

More Books

Students also viewed these Accounting questions

Question

Find the zero(s) of the function f(x) = 3x + 9.

Answered: 1 week ago

Question

What is a key public for this product/service/concept?

Answered: 1 week ago