5. You are the PM for the Atlas project. The project budget is $200,000 and has earned 10% of the project value. Due to unforeseen
5. You are the PM for the Atlas project. The project budget is $200,000 and has earned 10% of the project value. Due to unforeseen circumstances, you had to spend $25,000 to complete 10% of the work. What is the cost variance