54 (Mandatory) (1 point) In project time management, the process of_____ primarily involves checking and managing changes to the project schedule. Question 54 options: a)
54 (Mandatory) (1 point) In project time management, the process of_____ primarily involves checking and managing changes to the project schedule. Question 54 options: a) developing the schedule b) estimating activity resources c) controlling the schedule d) estimating activity durations