57. A planning process that identifies the threats to a project and has as its objective the reduction in the probability of these threats is
57. A planning process that identifies the threats to a project and has as its objective the reduction in the probability of these threats is called Scope Control Schedule Decomposition Control Enhancement Risk Mitigation 58. If an activity takes 21 weeks and the earliest it can start is week 41, when is the latest it can start if it is on the critical path. Week 41 Week 52 Week 62 Not enough information given