6 2 points A cost-plus-incentive-fee contract has the following characteristics: . Sharing ratio: 80/20 . Target cost: $100,000 . Target fee: $12,000 . Maximum fee:

image text in transcribedimage text in transcribed
image text in transcribedimage text in transcribed
6 2 points A cost-plus-incentive-fee contract has the following characteristics: . Sharing ratio: 80/20 . Target cost: $100,000 . Target fee: $12,000 . Maximum fee: $14,000 Minimum fee: $9,000 How much will the contractor be reimbursed if the cost of performing the work is $95,000? O $114,000 O $108.000 $98,000 O $100,0007 2 points A fixed-price-incentive-fee contract has the following characteristics: . Sharing ratio: 70/30 . Target cost: $100,000 . Target fee: $8,000 Price ceiling: $110,000 how much will the contractor be reimbursed if the cost of performing the work is $102,000? O $109,400 O $107,400 O $104,000 O $110,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cases In Hospitality Management A Critical Incident Approach

Authors: Timothy R Hinkin

1st Edition

0471112178, 9780471112174

More Books

Students also viewed these General Management questions

Question

What is the most common method of producing metal powders?

Answered: 1 week ago

Question

2. It is the results achieved that are important.

Answered: 1 week ago