6. Sally contracted to supply a propeller, without delay, to Gary's factory since one of the machine's propellers in Gary's factory was broken. Sally unreasonably

6. Sally contracted to supply a propeller, without delay, to Gary's factory since one of the

machine's propellers in Gary's factory was broken. Sally unreasonably delayed the

delivery of the propeller to Gary's factory. Gary sued Sally for breach of contract and

sought damages from Sally for the following losses:

(a) Loss of profit approximately RM2 million due to the delay.

(b) Loss of a profitable contract with the Government.

Advise Gary on whether he can claim damages from Sally for the losses above.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Law For Health Informatics And Information Management

Authors: Melanie Brodnik, LaurieRinehart-Thompson, Rebecca Reynolds

3rd Edition

9781584265306

More Books

Students also viewed these Law questions

Question

=+b) Is this model appropriate for this series? Explain.

Answered: 1 week ago

Question

Always show respect for the other person or persons.

Answered: 1 week ago

Question

Self-awareness is linked to the businesss results.

Answered: 1 week ago

Question

1. Too reflect on self-management

Answered: 1 week ago