Question

1 Approved Answer

6 . with reactive crashing ( compared to pro - active crashing ) a . the tradeoff between cost and time changes, and the same

6. with reactive crashing (compared to pro-active crashing)
a. the tradeoff between cost and time changes, and the same time savings can be achieved at lower cost
b. the project manager needs to develop decison-points where the contigency crashng plan will be implemented based on project status.
c. the project status manager needs the ability to rellocated resources on short notices
d. all of the above
8. We assumed in Q2 that duration of B might be 2 or 8 with equal likelihood. If duration of B is 2 with 20% chance and 8 with 80% chance, then the value of flexibility
a. increases
b. decreases
c. remain the same
9. We assumed in Q2 that duration of B might be 2 or 8 with equal likelihood. If duration of B is 2 with 80% chance and 8 with 20% chance, then the value of flexibility
a. increases
b. decreases
c. remain the same
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding Management

Authors: Richard L Daft, Dorothy Marcic

6th Edition

9780324581782, 324581785, 978-0324568387

More Books

Students also viewed these General Management questions