Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

7 . A project manager expects that the project would finish one month before the planned finish date. However he expects that the project to

7. A project manager expects that the project would finish one month before the planned
finish date. However he expects that the project to exceed the budgeted cost. What is true
about the Schedule Performance Index (SPI)
SPI is equal to 1.0
SV is less than 0
SPI is greater than 1.0
SPI is less than 1.0
8. Earned Value Measurements of a project indicate that the current CPI is 0.80 and the
current SPI is 0.98. For the next phase of the project the project manager should focus on
which element of the project.
Stakeholder Engagement
Schedule
Change control process
Cost
9. SPI greater than one implies that
Project is ahead of schedule
Project progress is according to the baseline plan
Project is behind schedule
Earned Value (EV) is less than Planned Value (PV)
10. At the end of the project schedule variance is equal to
Zero
Earned Value
One
Planned Value
11. How much we will be over or under budget at the end of the project; is expressed by?
Estimate to Complete (ETC)=(BAC EV)/ CPI
To-Complete Performance Index (TCPI)=(BAC EV)/(BAC AC)
Variance at Completion (VAC)= EAC BAC
Estimate at completion (EAC )= BAC / CPI
12. What is the upper limit imposed on Actual Cost (AC)
AC does not have any upper limit
Depends on the nature of the project
AC is limited to 2 times the planned value
AC is limited to 3 times the planned value
13. A project manager determined that BAC is no longer viable and developed a forecasted
EAC. What index can the project manager use to look at the calculated projection of cost
performance that must be achieved on the remaining work.
Cost Variance (CV)
To Complete Performance Index (TCPI)
Cost Performance Index (CPI)
Variance at Completion (VAC)
14. Schedule Variance (SV) less than zero implies that
Schedule progress is as per the baseline plan
Project is behind schedule
Earned Value (EV) is greater than Planned (PV)
Project is ahead of schedule
15. The Earned Value Methodology (EVM) can be used as a means to
Calculate the number of days left in the project
Calculate the profitability of the project
Calculate the value provided to the customer
Forecast future performance based on past performance
16. Work remaining on the project is expressed as
EAC - AC
BAC - AC
BAC - EV
BAC - EC
17. Which of the following formulas answers the question; What is the remaining work likely
to cost?
To-Complete Performance Index (TCPI)=(BAC EV)/(EAC AC
Estimate to Complete (ETC)=(BAC EV)/ CPI
Estimate at completion (EAC)= AC + Bottom up ETC
Variance at Completion (VAC)= EAC

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: David Anderson, Dennis Sweeney, Thomas Williams, Jeffrey Cam

12th Edition

840062338, 840062346, 9780840062338, 978-0840062345

More Books

Students also viewed these General Management questions

Question

What is the UK Corporate Governance Code?

Answered: 1 week ago