Answered step by step
Verified Expert Solution
Question
1 Approved Answer
7 . A project manager expects that the project would finish one month before the planned finish date. However he expects that the project to
A project manager expects that the project would finish one month before the planned
finish date. However he expects that the project to exceed the budgeted cost. What is true
about the Schedule Performance Index SPI
SPI is equal to
SV is less than
SPI is greater than
SPI is less than
Earned Value Measurements of a project indicate that the current CPI is and the
current SPI is For the next phase of the project the project manager should focus on
which element of the project.
Stakeholder Engagement
Schedule
Change control process
Cost
SPI greater than one implies that
Project is ahead of schedule
Project progress is according to the baseline plan
Project is behind schedule
Earned Value EV is less than Planned Value PV
At the end of the project schedule variance is equal to
Zero
Earned Value
One
Planned Value
How much we will be over or under budget at the end of the project; is expressed by
Estimate to Complete ETCBAC EV CPI
ToComplete Performance Index TCPIBAC EVBAC AC
Variance at Completion VAC EAC BAC
Estimate at completion EAC BAC CPI
What is the upper limit imposed on Actual Cost AC
AC does not have any upper limit
Depends on the nature of the project
AC is limited to times the planned value
AC is limited to times the planned value
A project manager determined that BAC is no longer viable and developed a forecasted
EAC. What index can the project manager use to look at the calculated projection of cost
performance that must be achieved on the remaining work.
Cost Variance CV
To Complete Performance Index TCPI
Cost Performance Index CPI
Variance at Completion VAC
Schedule Variance SV less than zero implies that
Schedule progress is as per the baseline plan
Project is behind schedule
Earned Value EV is greater than Planned PV
Project is ahead of schedule
The Earned Value Methodology EVM can be used as a means to
Calculate the number of days left in the project
Calculate the profitability of the project
Calculate the value provided to the customer
Forecast future performance based on past performance
Work remaining on the project is expressed as
EAC AC
BAC AC
BAC EV
BAC EC
Which of the following formulas answers the question; What is the remaining work likely
to cost
ToComplete Performance Index TCPIBAC EVEAC AC
Estimate to Complete ETCBAC EV CPI
Estimate at completion EAC AC Bottom up ETC
Variance at Completion VAC EAC
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started