7. Consider the following set of activities: Activity Days Required Predecessors A 3 B 4 C 4 D 3 AAA A E 3 D
7. Consider the following set of activities: Activity Days Required Predecessors A 3 B 4 C 4 D 3 AAA A E 3 D F 4 B G 6 B | J 564 5 4 F,C,E G,H F,C,E K 2 D L 6 I,J,K a. Draw the CPM network for this problem. b. Calculate the earliest start time, earliest finish time, latest start earliest, latest finish time, and total slack for each activity. c. Calculate the total project duration and identify the critical path.