7. Match the number to the correct letter. 12 5 6 7 8 1. A. Early 2. B. Late 3. C. Start 4. D. Finish
7. Match the number to the correct letter. 12 5 6 7 8 1. A. Early 2. B. Late 3. C. Start 4. D. Finish 5. E. Early Start 6. F. Late Start 7. G. Early Finish 8. H. Late Finish 8. The critical path of any project is identified by which of the following? a. Zero float b. Longest path c. Shortest possible total duration d. All of the above 9. Which of the following formulae identifies the amount of float a work package has? a. ES-Duration b. LS-Duration c. LS-LF d. LS-ES 10. What are the elements defining risk? a. b. c