7 Roget Factory has budgeted factory overhead for the year at $3,682,000. It plans to produce 2,000,000 units of product. Budgeted direct labor hours are
7
Roget Factory has budgeted factory overhead for the year at $3,682,000. It plans to produce 2,000,000 units of product. Budgeted direct labor hours are 263,000, and budgeted machine hours are 750,000. Using a single plantwide factory overhead rate based on direct labor hours, the factory overhead rate for the year is Oa. $7.00 Ob. $14.00 Oc. $18.20 O d. $67.20Step by Step Solution