Question
71) Use the information in the table and assume that a worker is expected to devote half-time (four hours per day) to this project with
71) Use the information in the table and assume that a worker is expected to devote half-time (four hours per day) to this project with work taking place on a 5-day-per-week basis. If the project manager is told that the total number of hours per week cannot exceed 48, what is the first week that some resource leveling must occur?
Activity | Predecessor | Hours per Day | Time (Days) |
A | -- | 4 | 6 |
B | A | 4 | 11 |
C | A | 5 | 5 |
D | B | 4 | 6 |
E | B | 4 | 6 |
F | B | 6 | 3 |
G | C, D | 8 | 11 |
H | E, F | 8 | 8 |
J | G, H | 3 | 10 |
K | J | 6 | 4 |
A) Week 2
B) Week 6
C) Week 4
D) Week 5
72) A project consists of eleven activities (all times are given in days) and has worker requirements as indicated in the table. Assume that all six workers employed by this organization are generalists and are able to work on any of the tasks. What is the fastest the project can be completed?
Activity | Activity time | Workers Needed | Predecessor |
A | 10 | 1 |
|
B | 4 | 2 |
|
C | 7 | 3 | A |
D | 4 | 1 | A |
E | 8 | 2 | B |
F | 9 | 3 | C,E |
G | 13 | 1 | D |
H | 14 | 2 | E,G |
J | 13 | 3 | F |
K | 10 | 1 | H, J |
L | 5 | 2 | K |
A) 54 days
B) 56 days
C) 58 days
D) 60 days
73) A project consists of eleven activities (all times are given in days) and has worker requirements as indicated in the table. Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks. What is the fastest the project can be completed while constrained by the four worker limitation?
Activity | Activity time | Workers Needed | Predecessor |
A | 10 | 1 |
|
B | 4 | 2 |
|
C | 7 | 3 | A |
D | 4 | 1 | A |
E | 8 | 2 | B |
F | 9 | 3 | C,E |
G | 13 | 1 | D |
H | 14 | 2 | E,G |
J | 13 | 3 | F |
K | 10 | 1 | H, J |
L | 5 | 2 | K |
A) 68 days
B) 70 days
C) 66 days
D) 72 days
74) A project consists of eleven activities (all times are given in days) and has worker requirements as indicated in the table. Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks. What is the first day where this project exceeds the four worker maximum?
Activity | Activity time | Workers Needed | Predecessor |
A | 10 | 1 |
|
B | 4 | 2 |
|
C | 7 | 3 | A |
D | 4 | 1 | A |
E | 8 | 2 | B |
F | 9 | 3 | C,E |
G | 13 | 1 | D |
H | 14 | 2 | E,G |
J | 13 | 3 | F |
K | 10 | 1 | H, J |
L | 5 | 2 | K |
A) Day 10
B) Day 11
C) Day 12
D) Day 13
75) A project consists of eleven activities (all times are given in days) and has worker requirements as indicated in the table. Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks. What day does activity C start under a leveled project with the four worker limitation?
Activity | Activity time | Workers Needed | Predecessor |
A | 10 | 1 |
|
B | 4 | 2 |
|
C | 7 | 3 | A |
D | 4 | 1 | A |
E | 8 | 2 | B |
F | 9 | 3 | C,E |
G | 13 | 1 | D |
H | 14 | 2 | E,G |
J | 13 | 3 | F |
K | 10 | 1 | H, J |
L | 5 | 2 | K |
A) Day 13
B) Day 15
C) Day 17
D) Day 19
Show explanation
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started