71) Use the information in the table and assume that a worker is expected to devote half-time (four hours per day) to this project with

71) Use the information in the table and assume that a worker is expected to devote half-time (four hours per day) to this project with work taking place on a 5-day-per-week basis. If the project manager is told that the total number of hours per week cannot exceed 48, what is the first week that some resource leveling must occur?

Activity

Predecessor

Hours per Day

Time (Days)

A

--

4

6

B

A

4

11

C

A

5

5

D

B

4

6

E

B

4

6

F

B

6

3

G

C, D

8

11

H

E, F

8

8

J

G, H

3

10

K

J

6

4

A) Week 2

B) Week 6

C) Week 4

D) Week 5

72) A project consists of eleven activities (all times are given in days) and has worker requirements as indicated in the table. Assume that all six workers employed by this organization are generalists and are able to work on any of the tasks. What is the fastest the project can be completed?

Activity

Activity time

Workers Needed

Predecessor

A

10

1

B

4

2

C

7

3

A

D

4

1

A

E

8

2

B

F

9

3

C,E

G

13

1

D

H

14

2

E,G

J

13

3

F

K

10

1

H, J

L

5

2

K

A) 54 days

B) 56 days

C) 58 days

D) 60 days

73) A project consists of eleven activities (all times are given in days) and has worker requirements as indicated in the table. Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks. What is the fastest the project can be completed while constrained by the four worker limitation?

Activity

Activity time

Workers Needed

Predecessor

A

10

1

B

4

2

C

7

3

A

D

4

1

A

E

8

2

B

F

9

3

C,E

G

13

1

D

H

14

2

E,G

J

13

3

F

K

10

1

H, J

L

5

2

K

A) 68 days

B) 70 days

C) 66 days

D) 72 days

74) A project consists of eleven activities (all times are given in days) and has worker requirements as indicated in the table. Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks. What is the first day where this project exceeds the four worker maximum?

Activity

Activity time

Workers Needed

Predecessor

A

10

1

B

4

2

C

7

3

A

D

4

1

A

E

8

2

B

F

9

3

C,E

G

13

1

D

H

14

2

E,G

J

13

3

F

K

10

1

H, J

L

5

2

K

A) Day 10

B) Day 11

C) Day 12

D) Day 13

75) A project consists of eleven activities (all times are given in days) and has worker requirements as indicated in the table. Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks. What day does activity C start under a leveled project with the four worker limitation?

Activity

Activity time

Workers Needed

Predecessor

A

10

1

B

4

2

C

7

3

A

D

4

1

A

E

8

2

B

F

9

3

C,E

G

13

1

D

H

14

2

E,G

J

13

3

F

K

10

1

H, J

L

5

2

K

A) Day 13

B) Day 15

C) Day 17

D) Day 19

Show explanation

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions

Question

CL I P COL Astro- L(1-cas0) Lsing *A=2 L sin(0/2)

Answered: 1 week ago