Question
71.WHICH of the following is NOT a custom field that could be created in MS Project? A.Start B.Cost C.Outline D.Duration E.Text F.Baseline G.Number 72.WHICH of
71.WHICH of the following is NOT a custom field that could be created in MS Project?
A.Start
B.Cost
C.Outline
D.Duration
E.Text
F.Baseline
G.Number
72.WHICH of the following is NOT true about grouping data in MS Project?
A.Grouping changes the underlying structure of your plan
B.Grouping goes a step beyond sorting
C.Grouping reorganizes and summarizes the data in your plan
D.Grouping allows for a more refined level of data analysis and presentation
73.You can sort your project data in most views, regardless of the specific table used by the view or even if the view doesn't include a table at all.
TRUE
FALSE
74. WHICH of the following allows you to organize task or resource information according to criteria you choose and adds summary values at intervals you can customize?
A.sorting
B.filtering
C.renumbering
D.grouping
75.WHICH of the following is not possible to contain in a view?
A.tables
B.graphical charts
C.filters
D.dialog boxes
E.groups
76.What is the maximum number of baselines you can save in a single project plan?
A.29
B.3
C.99
D.1
E.11
F. 10 77.WHICH of the following is NOT saved as part of a baseline?
A.planned start dates
B.planned durations
C.planned costs of tasks
D.tracking actuals
78.The actual work values entered for one assigned are rolled up to the task, but do not affect the other assignments' work values on the task in WHICH of the following circumstances?
A.if a task has multiple resources assigned to it
B.if a task has no resources assigned to it
C.if a task has a single resource assigned to it
79.WHICH of the following should determine the level of tracking that best meets the needs of the project plan?
A.the project manager
B.the stakeholders
C.the corporate administration
D.the project team
E.the project resources
80.WHICH of the following is the difference between what you recorded to happen in the project plan and what was tracked in the plan as what actually happened?
A.the original plan
B.planningC.variance
D.actual work
E.tracking actuals
F.implementation
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started