73. You've recently been put in charge of redecorating the interior of your company's office. You had to order various furniture and decorative pieces, all
73. You've recently been put in charge of redecorating the interior of your company's office. You had to order various furniture and decorative pieces, all needing to be delivered and arranged within a month's time. To ensure everything goes according to plan, you set up weekly progress reports with he supplier to ensure nothing falls behind schedule. You're acting in which step of the project procurement management? O Plan Ocontrol O Close OConduct