76. There is a 2 percent error rate at a specific point in a production process. If an inspector is placed at this point, all

76. There is a 2 percent error rate at a specific point in a production process. If an inspector is placed at this point, all the errors can be detected and eliminated. However, the inspector is paid $9 per hour and can inspect units in the process at the rate of 50 per hour.

If no inspector is used and defects are allowed to pass this point, there is a cost of $10 per unit to correct the defect later on.

Assume that the line will operate at the same rate (i.e., the current production rate) regardless of whether the inspector is hired or not.

If an inspector is hired, what will be the inspection cost per unit?

Note: Round your answer to 3 decimal places.

If an inspector is not hired, what will be the defective cost per unit?

Note: Round your answer to 3 decimal places.

Should an inspector be hired based on costs alone?

  1. multiple choice

Yes

No

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Transport Operations

Authors: Allen Stuart

2nd Edition

978-0470115398, 0470115394

More Books

Students also viewed these General Management questions

Question

When might low quantities be justified for the die-casting process?

Answered: 1 week ago