8. Computers Unlimited sells microcomputers to universities and colleges and ships them from three distribution warehouses. The firm is able to supply the following numbers
8. Computers Unlimited sells microcomputers to universities and colleges and ships them from three distribution warehouses. The firm is able to supply the following numbers of microcomputers to the universities by the beginning of the academic year:
Distribution Supply
Warehouses (Microcomputers)
1. Cebu 420
2. Bacolod 610
3. Dumaguete 340
Total1,370
Four universities have ordered microcomputers that must be delivered and installed by the beginning of the academic year:
Demand
University (Microcomputers)
A. University of Visayas 520
B. University of Bacolod 250
C. Dumaguete University 400
D. Cebu University 380
1,550
The shipping and installation costs per microcomputer from each distributor to each university are as follows:
To (cost)
From A B C D
1 22 17 30 18
2 15 35 20 25
3 28 21 16 14
Solve this problem by using the computer.
9. In Problem 8, Computers Unlimited wants to better meet demand at the four universities it sup-plies. It is considering two alternatives: (1) expand its warehouse at Cebu to a capacity of 600, at a cost equivalent to an additional 6 in handling and shipping per unit; or (2) purchase a new warehouse in Cagayan that can supply 300 units with shipping costs of 19 to University of Visayas, 26 to University of Bacolod, 22 to Dumaguete University, and 16 to Cebu University. Which alternative should management select, based solely on transportation costs (i.e., no capital costs)?
10. Computers Unlimited in Problem 8 has determined that when it is unable to meet the demand for microcomputers at the universities it supplies, the universities tend to purchase microcomputers elsewhere in the future. Thus, the firm has estimated a shortage cost for each microcomputer demanded but not supplied that reflects the loss of future sales and goodwill. These costs for each university are as follows:
University Cost/Microcomputer
A. University of Visayas 40
B. University of Bacolod 65
C. Dumaguete University 25
D. Cebu University 50
Solve Problem 8 with these shortage costs included. Compute the total transportation cost and the total shortage cost.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started