8 . Mitch was hired as a contractor to finish his bathroom. He expects the job to take 8 0 hours to complete. To date

8. Mitch was hired as a contractor to finish his bathroom. He expects the job to take 80 hours to complete. To date Mitch has worked the following hours:
Monday 8
Tuesday 111/8
Wednesday 11(1)/(2)
Thrusday 5(1)/(2)
Friday 153/8
How much longer should the job take to be completed?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Routledge Handbook Of Integrated Reporting

Authors: Charl De Villiers, Warren Maroun, Pei-Chi Hsiao

1st Edition

0367233851, 978-0367233853

More Books

Students also viewed these Finance questions

Question

Do the lines of best fit for the men's and women's miles cross?

Answered: 1 week ago

Question

what is the most common challenge with a management buyout Explain

Answered: 1 week ago

Question

explain what is meant by redundancy

Answered: 1 week ago