Answered step by step
Verified Expert Solution
Question
00
1 Approved Answer
8a. For the following project, (a) List all predecessors of task 5. (b) List all predecessors of task 4. (c) List all predecessors of the
8a. For the following project, (a) List all predecessors of task 5. (b) List all predecessors of task 4. (c) List all predecessors of the network finish (F). 5% S 2 4 8b. When activity times are known with certainty, the critical path is defined as the set of activities on a path from the project's start event to its finish event that, if delayed, will delay the completion date of the project. Why must this definition be modified in situations where the activity times are not known with certainty? Are there dangers associated with not modifying the definition? 5%
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started