Question
9 a) What is the project completion date? Based on the given information regarding the activities for the project, the project length = _________weeks. Part
9
a) What is the project completion date?
Based on the given information regarding the activities for the project, the project length =
_________weeks.
Part 3
b) What is the total cost required for completing this project on normal time?
The total cost required for completing this project on normal time = ____________
c) If you wish to reduce the time required to complete this project by 1 week, which activity should be crashed, and how much will this increase the total cost?
The critical path with the longest length through the project is
_______________
.
Part 5
To speed up the project at the least additional cost, first crash the activity that has the lowest crash cost per week. Determine the crash cost per week for each activity on the critical path.
For activity A, the per week crashing cost =
(Enter your response as a whole number.)
Part 6
For activity D, the per week crashing cost =
(Enter your response as a whole number.)
Part 7
For activity G, the per week crashing cost =
(Enter
your response as a whole
number.)
Part 8
For reducing the duration of the project by one week, the activity that should be crashed first is activity
___________Part 9
The cost of the project based on the first activity selected for crashing will increase by
$
your response as a whole
number.)
Part 10
d) What is the maximum time that can be crashed?
Part 11
Path A - D - G is still critical. Of these critical activities, activity D has the lowest crash cost per week of
$70.
Therefore, crash activity D by 3 additional weeks to reduce the project completion time to
12
weeks.
Part 12
Note that activity D cannot be crashed any further, since it has reached its crash limit of
4 weeks.
Part 13
What is(are) the critical path(s) after crashing activity D down to
4 weeks? choose
A.
Both A - D - G and C - F are critical.
B.
Both A - D - G and B - E - G are critical.
.
C.
B - E - G is critical.
D.
A - D - G is still critical.
Part 14
Hence, any further crashing must be done to both critical paths.
Part 15
Determine the crash cost per week for activities on path B - E - G.
For activity B, the per week crashing cost = __________(Enter
your response as a whole
number.)
Part 16
For activity E, the per week crashing cost =
(Enter your response as a whole
number.)
Part 17
For activity G, the per week crashing cost =
(Enter
your response as a whole
number.)
Part 18
On each of these critical paths, identify one activity that can still be crashed. Also the total cost of crashing the project should be the smallest. Note that activity
__________
is common to both paths. That is, by crashing this activity, we will simultaneously reduce the completion time of both paths, which yields the smallest total cost.
Part 19
Therefore, crash activity G by
______weeks.
(Enter your response as a whole
umber.)
Part 20
Activity A can still be crashed by 1 week. On path B - E - G, crash activity
______
by 1 week.
Part 21
Note that the project cannot be crashed any further, since all activities on path A - D - G have reached its crash limit. The maximum weeks by which the project can be reduced by crashing =
____________
weeks.
Part 22
How much would costs increase?
Total cost of crashing the project to minimum (or maximum weeks possible) =
D's crash cost + G's crash cost + A's crash cost + E's crash cost =
$enter your response here.
(Enter your response as a whole
number.)
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technolo firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: a) Based on the given information regarding the activities for the project, the project length = weeksStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started