9 As a project manager, you create a critical path for a project. You add up the duration of the tasks on the critical path
9 As a project manager, you create a critical path for a project. You add up the duration of the tasks on the critical path from the beginning to the end. What type of pass method did you use to calculate the critical path? 1 point Backward pass Low pass Forward pass Sequential pass