9-26 Suppose that the annual forecast in aggregate terms is 1,800,000 units and Model A makes up two-thirds of sales and Model B makes up
9-26 Suppose that the annual forecast in aggregate terms is 1,800,000 units and Model A makes up two-thirds of sales and Model B makes up one third of sales. What is the master schedule for daily production for an even production rate throughout the year (20 working days/month). Show work. Model A Model B Share Annual Sales Monthly Production Master Schedule for Daily Production