Question

00
1 Approved Answer

A 50-meter tunnel must be constructed as part of a new aqueduct system for a city. Two alternatives are being considered. One is to build

A 50-meter tunnel must be constructed as part of a new aqueduct system for a city. Two alternatives are being considered. One is to build a full-capacity tunnel now for $500,000. The other alternative is to build a half-capacity tunnel now for $300,000 and then to build a second parallel half-capacity tunnel 20 years hence for $400,000. The cost of repair of the tunnel lining at the end of every 10 years is estimated to be $20,000 for the full-capacity tunnel and $16,00 for each half-capacity tunnel.

Determine whether the full-capacity tunnel or the half-capacity tunnel should be constructed now. Solve the problem by B/C ratio analysis using a 5% interest rate and a 50-year analysis period. There will be no tunnel lining repair at the end of the 50 years.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Finance questions