Question

00
1 Approved Answer

A.) Activity rates from Quattrone Corporation's activity-based costing system are listed below. The company uses the activity rates to assign overhead costs to products: Activity

A.)

Activity rates from Quattrone Corporation's activity-based costing system are listed below. The company uses the activity rates to assign overhead costs to products:

Activity Cost Pools Activity Rate
Processing customer orders $102.89 per customer order
Assembling products $2.98 per assembly hour
Setting up batches $54.89 per batch

Last year, Product F76D involved 4 customer orders, 475 assembly hours, and 25 batches. How much overhead cost would be assigned to Product F76D using the activity-based costing system?

$68,108.15

$1,346.00

$3,199.31

$1,372.25

B.)

Lehner Corporation has provided the following data from its activity-based costing accounting system:

Indirect factory wages $605,000
Factory equipment depreciation $348,000

Distribution of Resource Consumption across Activity Cost Pools:

Activity Cost Pools
Customer Orders Product Processing Other Total
Indirect factory wages 55% 20% 25% 100%
Factory equipment depreciation 20% 60% 20% 100%

The "Other" activity cost pool consists of the costs of idle capacity and organization-sustaining costs that are not assigned to products.

How much indirect factory wages and factory equipment depreciation cost would NOT be assigned to products using the activity-based costing system?

$0

$348,000

$605,000

$220,850

C.)

Umanzor Corporation uses activity-based costing to assign overhead costs to products. Overhead costs have already been allocated to the company's three activity cost pools as follows: Processing, $46,700; Supervising, $33,600; and Other, $24,200. Processing costs are assigned to products using machine-hours (MHs) and Supervising costs are assigned to products using the number of batches. The costs in the Other activity cost pool are not assigned to products. Activity data appear below:

MHs (Processing) Batches (supervising)
Product S5 18,400 1,250
Product F5 770 970
Total

19,170

2,220

What is the overhead cost assigned to Product S5 under activity-based costing? (Round your intermediate calculations to 2 decimal places.)

$18,925.00

$44,896.00

$63,821.00

$48,353.00

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions