a) An activity has a duration estimate that is best case = 3 days, most likely = 4 days, and worst case=6 days. What is
a) An activity has a duration estimate that is best case = 3 days, most likely = 4 days, and worst case=6 days. What is the standard deviation for the activity in days ?