Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

a. Assuming the following information from two complex projects in the health sector have been provided to aid you select a project base on

a. Assuming the following information from two complex projects in the health sector have been provided to 

a. Assuming the following information from two complex projects in the health sector have been provided to aid you select a project base on project risk factor. Table la. Risk Probability and Consequences of Project A Probability of Failure Project A Maturity Complexity Dependency Project B Maturity Table Ib. Risk Probability and Consequences of Project B Probability of Failure Complexity Dependency 0.3 0.5 0.7 i. ii. iii. Cost Schedule Reliability Performance 0.1 0.3 0.3 Avoid Exploit Transfer Cost Schedule Reliability Performance Consequences 0.2 0.1 0.3 0.4 Consequences (Decision rule of thumb:70%-100%-high, 30%-69%-medium, < 30%-low) 0.2 0.6 0.3 0.8 Required: Which of the projects will you select and why? b. Under what two (2) conditions each will you adopt the following project risk response options. a. Assuming the following information from two complex projects in the health sector have been provided to aid you select a project base on project risk factor. Table la. Risk Probability and Consequences of Project A Probability of Failure Project A Maturity Complexity Dependency Project B Maturity Table Ib. Risk Probability and Consequences of Project B Probability of Failure Complexity Dependency 0.3 0.5 0.7 i. ii. iii. Cost Schedule Reliability Performance 0.1 0.3 0.3 Avoid Exploit Transfer Cost Schedule Reliability Performance Consequences 0.2 0.1 0.3 0.4 Consequences (Decision rule of thumb:70%-100%-high, 30%-69%-medium, < 30%-low) 0.2 0.6 0.3 0.8 Required: Which of the projects will you select and why? b. Under what two (2) conditions each will you adopt the following project risk response options. a. Assuming the following information from two complex projects in the health sector have been provided to aid you select a project base on project risk factor. Table la. Risk Probability and Consequences of Project A Probability of Failure Project A Maturity Complexity Dependency Project B Maturity Table Ib. Risk Probability and Consequences of Project B Probability of Failure Complexity Dependency 0.3 0.5 0.7 i. ii. iii. Cost Schedule Reliability Performance 0.1 0.3 0.3 Avoid Exploit Transfer Cost Schedule Reliability Performance Consequences 0.2 0.1 0.3 0.4 Consequences (Decision rule of thumb:70%-100%-high, 30% -69%-medium, < 30%-low) 0.2 0.6 0.3 0.8 Required: Which of the projects will you select and why? b. Under what two (2) conditions each will you adopt the following project risk response options. a. Assuming the following information from two complex projects in the health sector have been provided to aid you select a project base on project risk factor. Table la. Risk Probability and Consequences of Project A Probability of Failure Project A Maturity Complexity Dependency Project B Maturity Table Ib. Risk Probability and Consequences of Project B Probability of Failure Complexity Dependency 0.3 0.5 0.7 i. ii. iii. Cost Schedule Reliability Performance 0.1 0.3 0.3 Avoid Exploit Transfer Cost Schedule Reliability Performance Consequences 0.2 0.1 0.3 0.4 Consequences (Decision rule of thumb:70%-100%-high, 30%-69%-medium, < 30%-low) 0.2 0.6 0.3 0.8 Required: Which of the projects will you select and why? b. Under what two (2) conditions each will you adopt the following project risk response options. a. Assuming the following information from two complex projects in the health sector have been provided to aid you select a project base on project risk factor. Table la. Risk Probability and Consequences of Project A Probability of Failure Project A Maturity Complexity Dependency Project B Maturity Table Ib. Risk Probability and Consequences of Project B Probability of Failure Complexity Dependency 0.3 0.5 0.7 i. ii. iii. Cost Schedule Reliability Performance 0.1 0.3 0.3 Avoid Exploit Transfer Cost Schedule Reliability Performance Consequences 0.2 0.1 0.3 0.4 Consequences (Decision rule of thumb:70%-100%-high, 30%-69%-medium, < 30%-low) 0.2 0.6 0.3 0.8 Required: Which of the projects will you select and why? b. Under what two (2) conditions each will you adopt the following project risk response options.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

ANSWER Based on the tables you provided Project A has a higher risk probability and consequences compared to Project B Specifically Project A has a higher probability of failure 03 higher cost 02 and ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting A Critical Approach

Authors: John Friedlan

4th edition

1259066525, 978-1259066528

More Books

Students also viewed these General Management questions

Question

Describe ERP and how it can create efficiency within a business

Answered: 1 week ago

Question

3. Identify the four major structures that compose a neuron.

Answered: 1 week ago

Question

2. Which animal species would have the longest axonspg78

Answered: 1 week ago