A B D 1 Standards for one of Patterson, Inc.'s products is shown below, along with actual cost data for the month: 2 3 Direct materials: 4 Standard 2.4 yards @ $2.75 per yard $6.60 5 Actual 3 yards @ $2.70 per yard $8.10 6 Direct labor: 7 Standard 0.6 hours @ $18,00 per hour 10.80 8 Actual 0.5 hours @ $22.00 per hour 11.00 9 Variable overhead: 10 Standard 0.6 hours @ $7.00 per hour 4.20 11 Actual 0.5 hours @ $7.10 per hour 3.55 12 13 Total cost per unit $21.60 $22.65 14 15 Excess of actual cost over standard cost per unit $1.05 16 17 Actual production for the month 13,500 units 18 Variable overhead is assigned to products based on direct labor hours. There 19 was no beginning or ending inventory of materials for the month. 21 Using formulas, compute the following. Input all numbers as positive amounts. Indicate whether the variances are For U. Write if statements for variance cells F30 to F47. Use cell references (formulas) for cells D53 - D60. Enter an For U to indicate the correct variance in cells F54 to F62 Sheeti 20 22 READY Attempts) 10/10 A B D E F H 30 Indicate whether the variances are For U. Write if statements for variance cells F30 to 447. Use 22 cell references (formulas) for cells D53 - D60. Enter an For U to indicate the correct variance in cells F54 to F62 23 24 25 Standard Cost Variance Analysis - Direct Materials 26 Standard Quantity Allowed for Actual Output at Standard Price 27 Actual Quantity of Input, at Standard Price 28 Actual Quantity of Input, at Actual Price 29 Materials quantity variance 31 Materials price variance 32 33 Standard Cost Variance Analysis - Direct Labor 34 Standard Hours Allowed for Actual Output at Standard Rate 35 Actual Hours of Input, at Standard Rate 36 Actual Hours of Input, at Actual Rate 37 38 Labor efficiency variance 39 Labor rate variance 40 41 Standard Cost Variance Analysis - Variable Manufacturing Overhead 42 Standard Hours Allowed for Actual Output at Standard Rate Actual Hours of Input, at Standard Rate Sheet1 READY F G H B E D 44 Actual Hours of Input, at Actual Rate 45 46 Variable overhead efficiency variance 47 Variable overhead rate variance 48 49 Using formulas, compute the amount of the unit cost difference 50 that is traceable to each of the variances computed above. 51 52 Materials: 53 Quantity variance 54 Price variance 55 Labor: 56 Efficiency variance 57 Rate variance 58 Variable overhead: 59 Efficiency variance 60 Rate variance 61 62 Excess of actual over standard cost per unit 63 65 66 Sheet1 READY Attempt(s) 10/10