Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

A B D E Problem 1. In your new role as a project financial analyst, you are tasked to evaluate project Tetra, a new and

image text in transcribed

image text in transcribed

A B D E Problem 1. In your new role as a project financial analyst, you are tasked to evaluate project Tetra, a new and innovative software that allows doctors from around the world to communicate current best practices in real time. The project has two phases: you may invest in the first, both, or neither. Phase 1 (Tetra 1) requires an initial investment of $100. One year later, Tetra 1 will produce project CFs of either $160 or $60, each with equal probability of occurrence. At this year 1 point and after cash flows have been received, you may invest an additional $100 for Tetra 2. One year later, Tetra 2 pays out either 20% more in project CFs than Tetra 1 or equally likely) 20% less. No taxes need to be 1 assumed. 2 Part 1 a: How much would the Tetra project be worth if it offered only the Tetra 1 opportunity? 3 Part 1 b: How much would Tetra be worth if you had to make the entire decision today, once and for all, whether or not to invest in Tetra? 4 Part 1 c: How much is Tetra project worth if you have access to both Tetra 1 and 2, but can wait to decide whether to invest in Tetra 2 after 1 year (i.e. can see Tetra 1 through)? Utilize Typing Numbers is okay The Scenario Labels Hints Equations/functions 5 6 7 0.10 required retum 8 0 1 9 10 Part 1 a 11 Tetra 1 best 12 Project CF 13 PV Project CFS 14 NPV 15 0 1 accept/reject? (choose 1) 0 1 2 16 Tetra 1 worst 17 CAPEX 18 PV Project CFS 19 NPV 20 NPV of whole project 21 22 Part 1 b 23 Tetra 1 best, Tetra 2 best 24 CAPEX 25 OCF 26 project CF 27 NPV 28 Tetra 1 best, Tetra 2 worst 29 CAPEX 30 OCF 31 project CF 32 NPV 33 Tetra 1 worst, Tetra 2 best 34 CAPEX 35 OCF 36 project CF 37 NPV 0 0 1 2 0 1 2 0 1 2 0 2 38 Tetra 1 worst, Tetra 2 worst 39 CAPEX 40 OCF 41 project CF 42 NPV 43 NPV overall accept/reject? (choose 1) 44 45 Part 1c 46 Tetra 2 best 1 47 CAPEX 48 OCF $0 $0 49 project CF 50 NPV tetra 2 best at year 1. $0.00 51 Tetra 2 worst 1 52 CAPEX 53 OCF $0 $0 54 project CF 55 NPV tetra 2 worst year 1. 56 NPV total tetra 2 at year 0. Hints: value Tetra 2 on it's own (ignore relevant CFs from Tetra 1). First at time 1, then 57 discount back to time 0. NPV for whole project & 58 option accept/reject? (choose 1) 0 2 Hints: You've already valued Tetra 1 in "Part 1a" (NPV from cell B27), now cell 863 is the NPV of Tetra 2, but remember the likelihood of taking on Tetra 2 is not 100%...calculate NPV of the whole project and the real option. 59 ro A B D E Problem 1. In your new role as a project financial analyst, you are tasked to evaluate project Tetra, a new and innovative software that allows doctors from around the world to communicate current best practices in real time. The project has two phases: you may invest in the first, both, or neither. Phase 1 (Tetra 1) requires an initial investment of $100. One year later, Tetra 1 will produce project CFs of either $160 or $60, each with equal probability of occurrence. At this year 1 point and after cash flows have been received, you may invest an additional $100 for Tetra 2. One year later, Tetra 2 pays out either 20% more in project CFs than Tetra 1 or equally likely) 20% less. No taxes need to be 1 assumed. 2 Part 1 a: How much would the Tetra project be worth if it offered only the Tetra 1 opportunity? 3 Part 1 b: How much would Tetra be worth if you had to make the entire decision today, once and for all, whether or not to invest in Tetra? 4 Part 1 c: How much is Tetra project worth if you have access to both Tetra 1 and 2, but can wait to decide whether to invest in Tetra 2 after 1 year (i.e. can see Tetra 1 through)? Utilize Typing Numbers is okay The Scenario Labels Hints Equations/functions 5 6 7 0.10 required retum 8 0 1 9 10 Part 1 a 11 Tetra 1 best 12 Project CF 13 PV Project CFS 14 NPV 15 0 1 accept/reject? (choose 1) 0 1 2 16 Tetra 1 worst 17 CAPEX 18 PV Project CFS 19 NPV 20 NPV of whole project 21 22 Part 1 b 23 Tetra 1 best, Tetra 2 best 24 CAPEX 25 OCF 26 project CF 27 NPV 28 Tetra 1 best, Tetra 2 worst 29 CAPEX 30 OCF 31 project CF 32 NPV 33 Tetra 1 worst, Tetra 2 best 34 CAPEX 35 OCF 36 project CF 37 NPV 0 0 1 2 0 1 2 0 1 2 0 2 38 Tetra 1 worst, Tetra 2 worst 39 CAPEX 40 OCF 41 project CF 42 NPV 43 NPV overall accept/reject? (choose 1) 44 45 Part 1c 46 Tetra 2 best 1 47 CAPEX 48 OCF $0 $0 49 project CF 50 NPV tetra 2 best at year 1. $0.00 51 Tetra 2 worst 1 52 CAPEX 53 OCF $0 $0 54 project CF 55 NPV tetra 2 worst year 1. 56 NPV total tetra 2 at year 0. Hints: value Tetra 2 on it's own (ignore relevant CFs from Tetra 1). First at time 1, then 57 discount back to time 0. NPV for whole project & 58 option accept/reject? (choose 1) 0 2 Hints: You've already valued Tetra 1 in "Part 1a" (NPV from cell B27), now cell 863 is the NPV of Tetra 2, but remember the likelihood of taking on Tetra 2 is not 100%...calculate NPV of the whole project and the real option. 59 ro

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essential Mathematics For Economic Analysis

Authors: Knut Sydsaeter, Peter Hammond

3rd Edition

0273713248, 9780273713241

More Books

Students also viewed these Finance questions

Question

What do I enjoy doing? What kinds of skills does this require?

Answered: 1 week ago

Question

Define and explain the goals of employee orientation/onboarding

Answered: 1 week ago