A bank is planning to install a new computerized accounts system. Bank management has determined the activities required to complete the project. The precedence relationships

A bank is planning to install a new computerized accounts system. Bank management has determined the activities required to complete the project. The precedence relationships of the activities, and activity time estimates as follows:

Activity Predecessor a (wks) m (wks) b (wks)
a -- 5 8 17
b -- 3 12 15
c a 4 7 10
d a 5 8 23
e b, c 1 1 1
f b, c 1 4 13
g d, e 3 6 9
h d, e 1 2.5 7
i h 1 1 1
j f, g 2 2 2
k g, i 5 8 11

  1. Construct the CPM network. (15 pts)
  2. Determine the earliest and latest activity start and finish times (show in the network). (5 pts)
  3. Calculate the probability that the project will be completed in 40 weeks or less. (5 pts)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials Of Accounting

Authors: Robert N. Anthony, Leslie Pearlman Breitner

9th Edition

013149693X, 9780131496934

More Books

Students also viewed these Accounting questions