A body and paint shop has five cars to schedule for repair. They would like to minimize throughput time to complete all work on these

A body and paint shop has five cars to schedule for repair. They would like to minimize throughput time to complete all work on these cars. Each car requires body work prior to painting. The estimates of the time required to do the body and paint work on each area are as follows:
CAR BODY WORK (hours)
A 37
B 14
C 21
D 23
E 32
PAINT (hours)21
16
17
3025
Notice that this is 127 hours of work for the body shop and 109 hours for the paint work.
assuming this schedule happens over a 3-4 week period and jobs will carry over from day to day with no effect on the time it takes to complete the job if it is stopped mid-way and started up again the next morning. In other words, treat the 100+ hours as a single continuous shift.
(A) What is the suggested sequence of processing (first car to last) by using Johnsons Rule for two- stage processing?
_______________
(B) What is the idle time in the paint department as a number of hours and as percentage of work- day? (include the time spent waiting for the first job to come to paint and ending at the time period when the last car leaves the paint department)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding Business Ethics

Authors: Peter A. Stanwick, Sarah D. Stanwick

3rd Edition

9781506303239

Students also viewed these General Management questions