Question
A building consultant has broken the project into a number of separate tasks identified by letters.Preliminary estimates of the normal time and cost have been
A building consultant has broken the project into a number of separate tasks identified by letters.Preliminary estimates of the normal time and cost have been provided:
Task Task Description Precedence Time (days) cost($) crash time (days) Per day revised cost
A Preparation of drawings and permits - 14 72,500 10 10,000
B Calling and letting of tenders - 68 1,66,750 66 23,000
C Site preparation and excavation A 6 1,16,000 4 16,000
D Pouring the foundation A 24 2,50,000 24 -
E Framing C,D 40 1,45,000 30 20,000
F Plumbing and electrical work D 18 1,59,500 12 22,000
G Interior finished F 16 1,08,750 12 15,000
H Exterior finishes E,G 22 1,75,000 22 -
I Installing and commissioning new machines B,E 34 1,01,500 30 14,000
J Finishing touches and final work through H,I 32 64,000 32 -
The building consultant has advised that the following relationship exists among these tasks:
A and B can be commenced at the same time.
C and D can both be commenced as soon as A is completed.
E cannot be commended until C and D are completed.
F can be commenced once D is completed.
G can be started once F is finished.
H cannot be commenced until E and G are completed.
I cannot start until B and E are completed.
J cannot commence until H and I are completed.
Required:
- Calculate the minimum time and associate cost in which the project could be completed. (8 marks)
- The building is nearing completion, Paige Turner has written into the contract penalty provisions if the work is not finished on time.The only remaining task to complete is J and so far it is on schedule to complete in time however there is still 12 days to go, the cost has increased from $2,000 per day to $3,500 per day. The building consultant, in discussion with Paige, feels that an investigation might be worthwhile.The cost to investigate is $4,000 per day which might show if there is problem and if this the case it can be rectified by $10,000.This would lead to the cost being reduced to $2,000 for the remaining days.The probability of being able to rectify the problem is 0.7, should the consultant investigate?(7 marks)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started