A building contractor is working on a vacation home and is looking over his schedule. He notices that the schedule calls for the foundation footers
A building contractor is working on a vacation home and is looking over his schedule. He notices that the schedule calls for the foundation footers to be poured and then the rough floor
decking to be installed. In this plan, the foundation footers would be an example of what types of activity?
Successor task
Lagactivity
Crashed activity
Predecessor task