A building manager hires a contractor to renovate their building. After 3 weeks, the contractor has renovated 6 out of 10 rooms in the building.
A building manager hires a contractor to renovate their building. After 3 weeks, the contractor has renovated 6 out of 10 rooms in the building. Assuming each room takes the same amount of work hours to renovate, what is the Schedule Forecast for the project?" 5 weeks 7 weeks 10 weeks 3 weeks