A business-critical project is in danger of missing a deadline in 15 days and failing. The team lead escalates the issue to management and is
A business-critical project is in danger of missing a deadline in 15 days and failing. The team lead escalates the issue to management and is given the option of adding an unknown resource for the next 2 weeks or reprioritizing the backlog. The project team asks the product owner to reprioritize the backlog. Why is this the best choice