Question

1 Approved Answer

A) Calculate the construction costs to be expensed in 2021. Construction costs = ? (Answer is not $4,785,000) B) Using the completed-contract method, calculate the

image text in transcribed

A) Calculate the construction costs to be expensed in 2021.

Construction costs = ? (Answer is not $4,785,000)

B) Using the completed-contract method, calculate the estimated gross profit that would be recognized during each year of the construction period.

Oriole Enterprises Ltd. has entered into a contract beginning in February 2020 to build two warehouses for Atlantis Structures Ltd. The contract is a non-cancellable fixed price contract for $9.7 million. The following data pertain to the construction period (all figures in thousands). 2020 2021 2022 Costs for the year $3,915 4,785 1,200 Estimated costs to complete 4.785 1,300 -0- Progress billings for the year (non-refundable) 3,590 4,210 1,900 Cash collected for the year 3,165 4,260 2,275

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions