A call center has been commissioned to call 4,000 people per week. The average time required for a call is 3 minutes. The telephone salesmen
A call center has been commissioned to call 4,000 people per week. The average time required for a call is 3 minutes. The telephone salesmen work 5 days a week and 8 hours a day. Under normal circumstances, staff take a 5-minute break every hour.
How many telemarketers must be assigned the assignment per week given the conditions above? Answers in integers
Step by Step Solution
There are 3 Steps involved in it
Step: 1