Question

1 Approved Answer

A certain project activity has an EF(early finish) of 11 and a late finish (LF) of 11. The total slack for this activity is: -8

image text in transcribed
A certain project activity has an EF(early finish) of 11 and a late finish (LF) of 11. The total slack for this activity is: -8 -12 0 24

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

CIA Part 3 Business Knowledge For Internal Auditing 2022

Authors: MUHAMMAD ZAIN

1st Edition

B09PM77HSC, 979-8794979688

More Books

Students also viewed these Accounting questions

Question

4. Devise an interview strategy from the interviewers point of view

Answered: 1 week ago