A certain project is made up of nine jobs. The associated precedence requirements and job processing times are as follows: Job Immediate Predecessors Time Required
A certain project is made up of nine jobs. The associated precedence requirements and job processing times are as follows: Job Immediate Predecessors Time Required (Weeks) A - 3 B - 5 C - 2 D - 4 E B, C 9 F C 7 G A, D, E 4 H E 5 I E, F 6 Which is the least critical job to the project (i.e., which job has the greatest slack)