Question
1 Approved Answer
a change order is required even if we are using the same material but from a different supplier because this is considered a deviation from
a change order is required even if we are using the same material but from a different supplier because this is considered a deviation from the plan, and also the change in supplier can affect various aspects of the project such as cost, quality or delivery timelines